Product Description
Ferric And Non Ferric Alum:
Alum are represented by the general formula R 1/2 SO4, R2"(SO4)3.24.H2O. Where R and R"are respectively monovalent and trivalent radicals. They are usually the double salts of ammonium, potassium or sodium sulphate with aluminum. Chromium or iron sulphate, and are readily prepared y by concentrating and cooling a solution containing molecular proportions of the Component Sulphate. Ferric and Non Ferric Alum is marketed in various grades. The cheapest grade called "alum cake". Potash alum also known as alum alumen. Ferric alumin is aluminum sulphate containing iron obtained from the bauxite ore. Potash alum is prepared from its naturally occurring minerals such as alunite and Ratinite, but in India these do not occur in appreciable quantities. Alum was formerly prepared from alum shales by roasting them in year and leaching it out with water. Alum is now produced in India by crystallizing together equivalent produced in India by Crystallizing together equivalent proportion of potassium sulphate and aluminiu sulphate. The solution is concentrated and the crystals are separated out are melted to yield lump alum or recrystalized to obtain large crystals. Aluminum Sulphate is covered by three different grade specifications, namely, technical, pure and analytical reagent grade.
Cost Estimation:
Plant Capacity 15 MT./Day
Land & Building (Area 5000 sq.mt.) Rs. 2.25 Cr.
Plant & Machinery Rs. 91 Lacs
W.C. for 3 Months Rs. 1.09 Cr.
Total Capital Investment Rs. 4.36 Cr.
Rate of Return 24%
Break Even Point 56%
Note: ITI can modify the Capacity and Project Cost based on your requirement.
Contents of the Project Reports
Introduction:
Uses and Applications
Properties
Market Position
Present Manufacturers
Detailed Process of Manufacture
Formulations
B.I.S. Specifications
Process Flow Sheet Diagram, Plant Layout,
Cost Economics with Profitability Analysis
Capacity
Land & Building Requirements with Rates
List & Details of Plant and Machinery with their Costs
Raw Materials Details/List and Costs
Power & Water Requirements
Labour/Staff Requirements
Utilities and Overheads
Total Capital Investment
Turnover
Cost of Production
Break Even Point
Profitability
Land Man Ratio
Suppliers of Plant & Machineries and Raw Materials
Cash Flow Statement
Repayment Schedule
Interest Chart
Depreciation Chart
Projected Balance Sheet for 5 Years etc.