10 MW GRID INTERACTIVE SOLAR POLYCRYSTALLINE PV POWER PLANT [CODE NO. 1652]
Grid interconnection of photovoltaic (PV) power generation system has the advantage of more effective utilization of generated power. However, the technical requirements from both the utility power system grid side and the PV system side need to be satisfied to ensure the safety of the PV installer and the reliability of the utility grid. Clarifying the technical requirements for grid interconnection and solving the problems are therefore very important issues for widespread application of PV systems. Grid interconnection of PV systems is accomplished through the inverter, which convert DC power generated from PV modules to AC power used for ordinary power supply for electrical equipments. Inverter system is therefore very important for grid connected PV systems.
COST ESTIMATION
Plant Capacity 10 MEGA WATTS
Land & Building (120000 Sq.Mtr) Rs. 5.24 Cr
Plant & Machinery Rs. 56.00 Cr
W.C. for 2 Months Rs. 25.70 Lacs
Total Capital Investment Rs. 61.86 Cr
Rate of Return 21%
Break Even Point 60%
Note: ITI can modify the Capacity and Project Cost based on your requirement.
Contents of the Project Reports
Introduction
Uses and Applications
Properties
Market Position
Present Manufacturers
Detailed Process of Manufacture
Formulations
B.I.S. Specifications
Process Flow Sheet Diagram, Plant Layout,
Cost Economics with Profitability Analysis
Capacity
Land & Building Requirements with Rates
List & Details of Plant and Machinery with their Costs
Raw Materials Details/List and Costs
Power & Water Requirements
Labour/Staff Requirements
Utilities and Overheads
Total Capital Investment
Turnover
Cost of Production
Break Even Point
Profitability
Land Man Ratio
Suppliers of Plant & Machineries and Raw Materials
Cash Flow Statement
Repayment Schedule
Interest Chart
Depreciation Chart